Practical completion and handover inspections for new homes

Your builder says the house is nearly finished and wants to walk through it with you and sign a defects list. You can have your own inspector check the work. We look over the finished home for visible defects and incomplete work, and give you a written report with photos to raise with your builder. HFT Building & Pest Inspections is a division of HFT Construction Pty Ltd (QBCC Licence No. 15096995), based in Brookwater in the City of Ipswich, Queensland.

A finished, furnished living room with floor-to-ceiling glass doors

What a practical completion inspection is

The Queensland Building and Construction Commission (QBCC) describes practical completion as the point where the building work is essentially finished and can be used for its intended purpose. For a domestic building contract, the definition in the QBCC Act is more precise: the work must be completed in line with the contract and the statutory requirements, with no defects or omissions other than minor ones that will not unreasonably affect occupation.

At this point you walk through the home with your builder. Defects and incomplete work go on a defects list, which the QBCC says is usually signed by both of you. It also says you can engage a building inspector to check the work on your behalf, at your own cost. That check is a practical completion, or handover, inspection: a visual inspection of the finished home that you book yourself.

When to book: after the builder's notice, before the final payment

The QBCC says your builder will tell you when the home is nearing practical completion, generally at least two to three weeks ahead, with at least five days' written notice. Contact us when that first notice arrives, with the date your builder has proposed.

On the QBCC New Home Construction Contract (version 3, July 2023) the window is short. After the builder's two written notices (GC 28.1 and 28.2), you or your representative inspect the work with the builder on the notified date or within 2 business days (GC 28.3). If you are satisfied it has reached practical completion, and the builder gives you written evidence that the required inspections and approvals are done, the builder signs a Form 6 Defects Document (or a similar document) and gives you a Form 7 Certificate of Practical Completion. The builder then hands over the home in exchange for payment of the practical completion stage claim, the final payment under the contract, which you must pay immediately (GC 28.6).

That puts your own inspection between the builder's notice and the final payment. The QBCC says you get the keys at handover, so ask your builder early about access. Other contracts use different clauses and forms, so check yours. This is general information, not legal advice.

We confirm the inspection time and the report timing when you book.

What we look at

The inspection is visual and covers what we can see and safely reach on the day. We confirm the scope with you when you book. Typically we record visible defects and work that looks unfinished, including:

  • Finishes inside and out: paint, plasterboard, cornices, tiling, joinery, cabinetry, benchtops, floor coverings, brickwork and cladding.
  • Doors and windows: frames, glass, seals and hardware, and doors or windows that bind, don't latch or don't close properly.
  • Wet areas: cracked or chipped tiles, gaps in grout or silicone, and floors that look unlikely to drain to the waste.
  • The roof space and eaves, where there is safe access: visible damage, signs of water getting in, displaced insulation and building debris left behind.
  • External drainage: whether the ground and paths fall away from the house, where downpipes discharge, and low spots where water may pond against the slab.
  • Retaining walls, when they are in the scope we agree at booking: visible cracking, leaning, bulging and water seeping through.
  • Missing and unfinished items: fittings, fixtures, trims, cover plates and touch-ups.

What it does not cover

A visual inspection shows the finish and visible condition of the home. It cannot see inside walls or under the slab, and it does not replace the certificates your builder and certifier provide. It does not include:

  • Plumbing or gas pressure tests, or electrical testing or certification. The QBCC lists certificates for electrical, plumbing and gas work among the documents to get before handover.
  • Engineering or geotechnical assessment. We don't assess the structural design of footings, the slab, framing or retaining walls. Where we see an issue outside the inspection, we may recommend a suitably qualified specialist, such as an engineer.
  • Hidden areas and areas we can't safely reach: wall cavities, under the slab, under fixed floor coverings, and anything locked, obstructed or unsafe to access.
  • Compliance certification. Our report is not a certifier's final inspection certificate (Form 21) or a waterproofing certificate.
  • A promise about the future. The report records what was visible on the day, and some defects only appear after months of use and weather.

How the report helps with your builder

You get a written report with photos, in plain English, setting out the visible defects and unfinished work we found, so you can raise each item with your builder.

Under the QBCC Act, the defects document lists the minor defects and omissions you and the builder agree on, with when they will be fixed, and also the items you say exist that the builder disputes. The builder signs it, so a disputed item still goes on record. On the QBCC template contract, the Certificate of Practical Completion is not an approval of the work and does not prejudice your claims about it (GC 28.5).

If items are still outstanding after handover, the QBCC says to give your builder written notice of every defective or unfinished item, with a timeframe to fix it (for example 14 days), and keep a copy, before you lodge a complaint. It also says clear photographs help a complaint progress.

The defects period, and a recheck before six months

Handover is not your last chance to raise defects. The QBCC says a contractor must repair any defects noticed at handover or within 12 months of when the work is finished, and you must tell the contractor within 12 months of noticing them. It also says a contract for a new build should include a defects liability period of 6 or 12 months, so check yours. If your builder doesn't fix a non-structural defect, the QBCC says a complaint must be lodged as soon as possible and no later than 12 months from completion of the work.

The Queensland Home Warranty Scheme has tighter time limits, which is why six months matters. Under the scheme's claim conditions, a non-structural defect is covered if you first become aware of it within 6 months after the day the work is substantially complete, and you make the claim within 7 months after that day. These are conditions for a claim on the scheme, not a limit on what your builder must fix. Structural defects have different limits, and the claim must be made within 3 months of first becoming aware of the defect. Home warranty cover is compulsory for residential construction work valued at more than $3,300, and you can ask the QBCC to search whether your property has cover.

That is why we suggest a second inspection about four to five months after practical completion, before the six-month mark. Cracking, doors that start to bind, leaks and drainage problems can show up after some months of use and weather. Anything we find is then in writing, with time to give your builder written notice and, if it isn't fixed, to lodge a QBCC complaint within the scheme's seven months. Book it as a defect inspection.

Building a new home in Ipswich

If you are building in Springfield or the Ripley Valley, you are in the fastest-growing of Queensland's larger council areas. Among council areas of 5,000 people or more, Ipswich grew fastest in 2024-25 (3.5%). The ABS SA2 statistical area called Ripley grew 15.4% (an extra 3,131 people), the fastest of the state's SA2s with 2,000 people or more, and Springfield Lakes was Queensland's most populous SA2, with 29,522 people at 30 June 2025. These June 2025 figures are preliminary ABS estimates. Economic Development Queensland says the Ripley Valley Priority Development Area could eventually hold 48,750 homes. We are based in Brookwater, also in the City of Ipswich.

Common questions

Can I have my own inspector check the home before handover?

Yes. The QBCC says you can engage a building inspector to check the work on your behalf, at your own cost. On the QBCC template contract, you or your representative inspect the work with the builder (GC 28.3). Contracts differ, so check yours, tell your builder in advance and ask how access will work.

What if I don't think the home has reached practical completion?

Under the QBCC Act, practical completion allows only minor defects and omissions that will not unreasonably affect occupation. On the QBCC template contract, if you reasonably consider the work is not at practical completion, you give the builder written notice of what still needs doing (GC 28.4). Get advice from a solicitor or the QBCC before you refuse to sign or pay.

What if my builder won't add an item to the defects list?

Under the QBCC Act, the defects document also lists defects and omissions you say exist but the builder disputes. Ask for the item to be recorded that way, and keep your copy with our report and photos.

My lender is doing a final inspection. Do I still need one?

The QBCC notes that if you have a construction loan, your lender will also do a final inspection before it issues the final payment. Ask your lender what it covers and whether you get a copy, then decide whether you want your own.

When will I get the report?

We confirm the report timing when you book. Tell us your builder's walk-through date at the same time, so we can plan the inspection around it.

Do you do handover inspections in Ripley and Springfield?

Yes. HFT Building & Pest Inspections carries out practical completion (handover) inspections for new homes across the Springfield, Ripley, Augustine Heights and Redbank Plains estates and the rest of the City of Ipswich. HFT is based in Brookwater, inside the City of Ipswich. Send the address and the date your builder has proposed when you ask for a quote.